iDIG delivered a package of works valued at around $2.2 million on the Pakenham Level Crossing Removal Project. Main bulk earthworks and rock placement took place over a 12-week period. Our team delivered high-quality work on time and on budget.
Scope of works:
Excavation – cart and dispose of 10,000m3 of soil
Sub-grade preparation and soft spot rectification
Placement of over 11,500 tonnes of crushed rock and CTCR
Construction of 350m2 of covered walkways roofing structure
FRP of 700m2 of concrete walkways, footpaths and crossovers
Relocation of bus depot during occupation works (including site levelling, asphalt and concrete works)
PAKENHAM LEVEL CROSSING REMOVAL
iDIG delivered a package of works valued at around $2.2 million on the Pakenham Level Crossing Removal Project.
Sector
Rail
Client