iDIG delivered a range of civil construction works on the Greens Road/Cranbourne line upgrade. The package of works totalled $2 million, and the work was carried out over a scheduled seven-day road closure.
We provided workforce cover for 24 hours a day to meet the tight timeframe. The road opened to the public on time, with all works delivered to the highest standard.
Scope of works:
Asphalt – 3,000m2 of resurfacing
Full-depth pavement (including placement of CTCR – 250m2)
Concrete pavement placement (750m2 including barrier infill and traffic island infill)
Pre-cast and in situ-barrier installation – 135m
Installation of 1km of subsoil drainage
Installation of various road signage
Management of road furniture sub-contractor, installing 170LM of guardrail
Management of line-marking sub-contractor installing 1km of line marking
Management of electrical sub-contractor installing eight light poles
Management of kerb sub-contractor installing 630 LM
Installation of 1km of shared user path including handrail, line marking and street lighting
GREENS ROAD CRANBOURNE LINE UPGRADE
McConnell Dowell contracted iDIG to deliver a range of civil construction works on the Greens Road/Cranbourne line upgrade.